On a project, pumps are often bought on price after a technical submittal. That works only if the quotations being compared actually meet the same duty and scope. This guide is for MEP contractors, consultants and procurement teams who need to compare pump offers on a fair basis.
1. Confirm the duty point
The duty point (flow and head) is the starting point. Ask each supplier for the pump curve with the duty point marked. Check that:
- The pump meets the flow at the specified head without running at the end of its curve
- The duty point is close to the best efficiency point
- The motor is not overloaded anywhere on the curve (non-overloading selection)
- NPSH required is below NPSH available on site, with a margin
Two pumps quoted for the same duty can have very different curves. The cheaper one may only meet the duty with a trimmed impeller at low efficiency, or not at all.
2. Compare efficiency
Pump efficiency and motor efficiency class affect running cost for the life of the installation. For pumps that run many hours a year, such as chilled water and booster pumps, a few percentage points of efficiency can be worth more than the difference in purchase price.
A simple check: annual energy cost is roughly motor input power multiplied by running hours and tariff. Compare this across offers.
3. Check materials
Confirm the casing, impeller, shaft and seal materials match the specification. Common substitutions to watch for:
- Cast iron impellers where bronze or stainless steel was specified
- Lower grade stainless steel
- Seals not rated for the water temperature or quality
4. Check the scope of supply
Quotations often differ in what is included:
- Base frame, coupling and guard
- Motor, and whether it is the specified brand and efficiency class
- Control panel, VFDs, and their enclosure ratings
- Pressure vessels, valves, strainers, gauges and flexible connectors
- Level controls and sensors
- Delivery to site, offloading, installation, testing and commissioning
- Operation and maintenance manuals, training and spare parts
Put all offers in a single comparison sheet with the same scope lines.
5. Approvals and compliance
Check that the offer meets project requirements for:
- Consultant approval and the approved manufacturers list
- Civil defence approval where pumps serve fire systems
- Potable water approvals for pumps in contact with drinking water
- Country of origin, if specified
6. Delivery time
Lead time affects the programme. Stock items ship quickly; factory-built sets and large pumps can take several weeks. Confirm lead time in writing.
7. Warranty and support
Ask about warranty length and what it covers, local spare parts stock, and the supplier’s ability to commission and service the equipment. A pump with no local support can become expensive when it needs a seal or bearing.
8. Lifecycle cost
For most building pumps, the purchase price is a small part of the total cost over 15 years. Energy and maintenance make up most of it. A lifecycle view usually favours a correctly sized, efficient pump with VFD control.
A simple comparison template
| Item | Offer A | Offer B | Offer C |
|---|---|---|---|
| Flow at duty head | |||
| Efficiency at duty | |||
| Motor kW and class | |||
| Materials | |||
| Control panel and VFD | |||
| Accessories included | |||
| Installation and commissioning | |||
| Lead time | |||
| Warranty | |||
| Price |
Frequently asked questions
Why are some pump quotes much cheaper?
Usually because of a smaller pump, lower efficiency, different materials, or a narrower scope. Check the curve and the inclusions.
Is it worth paying more for a VFD?
For pumps with variable demand, usually yes. See how VFDs reduce pump energy use.
Can Lifeline review a pump schedule?
Yes. Send the schedule and specification and we will propose selections with curves for each duty.